Job
Description :
Additional Gate (4
unit) & Motorization (10 unit) for Intake Canal on Siteki & Plumbungan
Micro Hydro Power Plant
Period : August 2011 - October 2011
Sluice Gate Model (Type Slide) :
I. SITEKI SITE
Additional Gate (2 unit) & Motorization (4
unit)
Before Installation :
After Installation :
II. PUMBUNGAN SITE
Additional Gate (2 unit) & Motorization (6
unit)
Before Installation :
After Installation :